1) Improved delivery predictability across multiple teams
-
At HelloFresh, I led a migration away from a legacy vendor with 8 months left on the contract.
-
I worked with the PM to map all use cases and dependencies, then with a staff engineer and partner teams to size the work and define migration paths.
-
We started with low-risk use cases first, then moved to a phased migration plan by team and week, which gave everyone clarity and reduced surprises.